Visitors talk at the overlook area of the East Branch Clarion River Lake in Wilcox, Pennsylvania, May 26, 2021, the day before the dam's grand reopening. The ceremony celebrates the completion of the $250 million, East Branch Clarion River Dam Safety Modification project. The project began in 2014 and consisted of constructing a 2200 linear feet cutoff wall that penetrates up to 250 feet down through the middle of the earthen dam. (U.S. Army Corps of Engineers Pittsburgh District photo by Michel Sauret)
Date Taken: | 05.26.2021 |
Date Posted: | 05.28.2021 16:40 |
Photo ID: | 6668598 |
VIRIN: | 210526-A-TI382-0334 |
Resolution: | 6048x4024 |
Size: | 7.53 MB |
Location: | WILCOX, PA, US |
Web Views: | 12 |
Downloads: | 3 |
This work, Cleaning up before cutting the ribbon on East Branch [Image 37 of 37], by Michel Sauret, identified by DVIDS, must comply with the restrictions shown on https://www.dvidshub.net/about/copyright.