Team Officer in Charge of Construction Pearl Harbor Naval Shipyard (OICC PHNSY) remains laser-focused as they work towards building the new Dry Dock 5 in 2026, but take a look at the various accomplishments the team achieved in 2025:
• OICC PHNSY achieved substantial progress on the new dry dock, progressing from 26 % to 47% in December and completing over $644M Work in Place over the year.
• A monumental accomplishment was the prefabrication of eight of the nine massive PFU floor units, each containing an average of 1.3 million pounds of steel and 1,800 cubic yards of concrete. These units, weighing up to 4,600 tons each and affectionately named after the Hawaiian islands, were transported by barge from the Waipio pre-cast yard...
Naval Facilities Engineering Systems Command (NAVFAC) Pacific awarded a $2.8-billion task order under a previously-awarded indefinite-delivery/indefinite-quantity multiple-award construction contract to Dragados/Hawaiian Dredging/Orion JV, based in Honolulu, Hawaii, to replace Dry Dock 3 at Pearl Harbor Naval Shipyard and Intermediate Maintenance Facility (PHNSY & IMF) March 10.