Embankment placement at West Shore Lake Pontchartrain contract 109 is moving along, with the tie-in to Contract 108 nearly complete. West and east pre-load areas have reached elevation 17’ and are now under a hold period. The west levee is at elevation 4.5’, and the east levee has reached its final elevation of 8.6’. Geotechnical instrumentation at the West Preload site is complete, ensuring a strong, stable foundation for the next phases of the project. Stay tuned as we continue building safer, stronger infrastructure for the future!