As of the first week of August, Fort McCoy’s South Barracks Project was edging ever closer to completion with a variety of work being completed.
Nathan Butts with the Resident Office of the U.S. Army Corps of Engineers said Fort McCoy’s South Barracks Project has reached 95 percent complete in his Aug. 8 update about the project.
The contractor for the project, BlindermanPower (Construction), received the notice to proceed with construction on Sept. 26, 2023, and has 780 calendar days to complete the project. At this point, Butts said the project is on time.
As stated in previous news updates, the project requires building a four-story, 60,000-square-foot barracks that can house 400 people. Two other barracks of the same specifications have already been built in the same block at the installation since 2019.
Fort McCoy Directorate of Public Works officials said overall this project is part of a big transformation taking place at the 1600 block that includes the building of four barracks — two of which are already done, three brigade headquarters buildings, and two planned transient training officer quarters, according to the Fort McCoy Directorate of Public Works.
In the Aug. 8 update, Butts also wrote everything that is getting completed.
“Contractor is working on their punch-list items,” Butts wrote. “Contractor replacing several floor tiles. Exterior site work continues. Parking lot concrete control joints cutting continues, sealant to follow.”
Also in previous updates, Fort McCoy leaders have spoken about the importance of the installation’s economic impact. It’s been stated that the installation’s vast training space and facilities attract training opportunities for many units to come to the post, which also affects economic impact.
It’s also been stated how Fort McCoy has 48,000 training acres and 3,000 cantonment acres. The importance of that, as it was shown, means the Army puts a lot of money into the installation, such as millions in new construction like these barracks projects.
Read more about about Fort McCoy’s economic impact by visiting https://www.dvidshub.net/news/496366/fort-mccoys-total-economic-impact-16-billion-during-fiscal-year-2024.
The South Barracks Project is one of three major projects currently happening at Fort McCoy, Another barracks project — the $27.3 million Fort McCoy East Barracks Project — and the $55.75 million Collective Training Officers Quarters Project.
See more news about the U.S. Army Corps of Engineers by visiting https://www.usace.army.mil/Media/News.
Fort McCoy’s motto is to be the “Total Force Training Center.” Located in the heart of the upper Midwest, Fort McCoy is the only U.S. Army installation in Wisconsin.
The installation has provided support and facilities for the field and classroom training of more than 100,000 military personnel from all services nearly every year since 1984.
Learn more about Fort McCoy online at https://home.army.mil/mccoy, on Facebook by searching “ftmccoy,” on Flickr at https://www.flickr.com/photos/fortmccoywi, on X (formerly Twitter) by searching “usagmccoy,” on Instagram at https://www.instagram.com/fortmccoywi, and on YouTube at https://www.youtube.com/@fortmccoy.
Also try downloading the My Army Post app to your smartphone and set “Fort McCoy” or another installation as your preferred base. Fort McCoy is also part of Army’s Installation Management Command where “We Are The Army’s Home.”
Date Taken: | 08.18.2025 |
Date Posted: | 08.18.2025 18:36 |
Story ID: | 545903 |
Location: | FORT MCCOY, WISCONSIN, US |
Web Views: | 58 |
Downloads: | 0 |
This work, South Barracks Project at Fort McCoy is 95 percent complete; soon to be finished, ready for turnover, by Scott Sturkol, identified by DVIDS, must comply with the restrictions shown on https://www.dvidshub.net/about/copyright.