    Engineers Work to Keep Clean Water Flowing to Iraqis

    Chemical Officer Inspects Oil Spill in Iraqi Waterway

    Courtesy Photo | Maj. John Gossett, chemical officer, 926th Engineer Group, attached to the 101st...... read more read more

    WASHINGTON, UNITED STATES

    12.03.2003

    Courtesy Story

    Defense.gov         

    American engineers in northern Iraq are using their skills to keep the water flowing into the people's houses in Mosul -- and to keep the oil out.

    In October a crude oil pipe ruptured, spilling an "unknown quantity" of oil into a dry creek bed 15 kilometers above the Tigris River. The Tigris is the source of water for millions of people in northern Iraq, said Maj. Scott Vick, group plans officer, 926th Engineer Group, attached to the 101st Airborne Division.

    The oil pooled in the creek bed until Thanksgiving weekend, when large torrents of rain created an intermittent creek, flushing much of the oil into the Tigris, Vick said.

    The oil was then sucked into the intake duct filters at the nearby water treatment plant. The crude clogged the system, forcing plant workers to temporarily shut it down, said Maj. John Gossett, the 926th's chemical officer.

    . Shutting down the plant, the clean-water source for Mosul and the surrounding region, affected food preparation and people's ability to drink and bathe.

    Cleaning oil out of the water tanks was a complicated job. Because the treatment plant was built on an old design, the water tanks are concrete. The oil soaked into the concrete and made the scrubbing process that much more difficult, Gossett said.

    To keep that incident from repeating, engineers attached to the 101st built a dam to keep the water from being contaminated again, Vick said.

    Using their own construction equipment and with supplies provided by the Mosul government, engineers from the 926th Engineers Group and 877th Engineer Battalion built a dam in two days. "Everyone agrees that this is the best alternative to prevent oil from reaching the Tigris," Vick said.

    The dam was built using three 12-inch diameter pipes placed on the creek bottom, then rocks no larger than 16 inches were dropped on top of the pipes. Because oil floats on top of water, the rocks will collect the crude and keep it from going any further. The water will be able to flow through the submerged pipes, Vick said.

    The engineers got equipment and supplies to clean the creek for items such as absorbent booms and pads to stop the oil, skimmers to get the oil out of the water, protective suits for those cleaning the river and other tools to treat the water, Vick said. "This will be the only source of petroleum remediation equipment in northern Iraq," Vick said.

    (Spc. Joshua Hutcheson is a journalist assigned to the 101st Airborne Division.)

    Story by Spc. Joshua Hutcheson, USA, Special to American Forces Press Service