Maintenance window scheduled to begin at February 14th 2200 est. until 0400 est. February 15th

(e.g. yourname@email.com)

Forgot Password?

    Defense Visual Information Distribution Service Logo

    Fort McCoy's East Barracks Project nearly 40 percent complete as May 2025 passes mid-month

    May 2025 barracks construction operations for East Barracks Project at Fort McCoy

    Photo By Scott Sturkol | Contractors work on a new $27.3 million transient training troops barracks project,...... read more read more

    Fort McCoy's East Barracks Project was reported nearly 40 percent complete as of May 16, said Nathan Butts with the Resident Office of the Army Corps of Engineers at Fort McCoy.

    In his May 16 update, Butts said the contractors with L.S. Black Constructors were steadily making progress on the project.

    “Metal framing in the fourth floor continues. Drywall installation continues. Roofing assembly continues. And Mechanical, electrical, and plumbing rough-in continues on all floors," Butts said.

    "Brick ledge installation continues, door fame installation on all floors continues, and drywall finishing and painting continues with the mechanical, electrical, and (other) rooms," Butts wrote. "Interior spray foam insulation continues in the bays."

    Since a year ago in May 2024, construction of this barracks have been nonstop by the contractor who was awarded the project in February 2024. The exact contract amount for the project when it was awarded was $27,287,735.

    As the workers with L.S. Black Constructors work on this project, they can look over at two other barracks they constructed in the same block. They are a familiar name in the construction history at Fort McCoy, having not only built the first two of the 60,000-square-foot transient training troops barracks, but they also built the new brigade headquarters building located in the same block as the barracks buildings.

    The contract duration is scheduled for completion in 780 calendar days, Army Corps of Engineer contract documents show. “Current contract completion date is April 24, 2026,” Butts also wrote in the May 16 update.

    From the building description, when complete, the building will be able to house up to 400 people like the other completed barracks in the same block. According to the scope of work, it’s going to be “made of permanent construction with reinforced concrete foundations; concrete floor slabs; structural steel frames; steel stud infill; masonry veneer walls; prefinished standing seam metal roofing; heating, ventilation, and air conditioning capabilities; plumbing; mechanical systems; and electrical systems. Supporting facilities include land clearing, concrete sidewalk paving, general site improvements, and utility connections.”

    Work also continues in 2025 by contractors to prepare a large swath of the 1600 block on Fort McCoy’s cantonment area to construct the fiscal year 2024-funded $55.75 million Collective Training Officers Quarters Project by contractor BlindermanPower (Construction).

    Fort McCoy Directorate of Public Works planning officials said all the construction is done with projects on this part of Fort McCoy, it will demonstrate a major transformation of the block and hold lots of barracks space for troops training at the installation.

    See more news about the U.S. Army Corps of Engineers by visiting https://www.usace.army.mil/Media/News.

    Learn more about Fort McCoy online at https://home.army.mil/mccoy, on Facebook by searching “ftmccoy,” on Flickr at https://www.flickr.com/photos/fortmccoywi, and on X (formerly Twitter) by searching “usagmccoy.”

    Also try downloading the My Army Post app to your smartphone and set “Fort McCoy” or another installation as your preferred base. Fort McCoy is also part of Army’s Installation Management Command where “We Are The Army’s Home.”

    NEWS INFO

    Date Taken: 05.19.2025
    Date Posted: 05.20.2025 01:10
    Story ID: 498414
    Location: FORT MCCOY, WISCONSIN, US

    Web Views: 132
    Downloads: 0

    PUBLIC DOMAIN