West Shore Lake Pontchartrain contract 114a is one of the more recent contracts awarded and construction is currently taking place northwest of Garyville, LA, along the alignment. Here is an update on the construction activities taking place at this site:
- Clearing and grubbing is complete
- Continuing with excavation of drainage canal at Hope Canal
- Completed excavation of bypass canal at Prescott
- 84” culverts installed at Prescott
- Contractor is preparing for Pile Driver Analyzer testing, which is a dynamic load test used to evaluate the capacity of the piles and monitor their installation
Date Taken: | 05.28.2025 |
Date Posted: | 06.10.2025 10:12 |
Photo ID: | 9099659 |
VIRIN: | 250528-A-EV636-9522 |
Resolution: | 6048x4024 |
Size: | 15.42 MB |
Location: | NEW ORLEANS, LOUISIANA, US |
Hometown: | NEW ORLEANS, LOUISIANA, US |
Web Views: | 1 |
Downloads: | 0 |
This work, West Shore Lake Pontchartrain contract 114a construction update, by Melanie Oubre, identified by DVIDS, must comply with the restrictions shown on https://www.dvidshub.net/about/copyright.