    153MXS post MAFFS maintenance

    153 MXS post MAFFS maintenance

    Photo By 2nd Lt. Natalie Stanley | The 153rd Maintenance Squadron performs maintenance on a C-130 at the ISO dock Nov. 4,...... read more read more

    CHEYENNE, WY, UNITED STATES

    12.01.2012

    Story by Tech. Sgt. Natalie Stanley 

    153rd Airlift Wing

    CHEYENNE, Wyo. - With the end of a highly visible Modular Airborne FireFighting System season comes the not so visible, yet highly mission critical, aircraft maintenance phase.

    During the 2012 fire season, Wyoming Air National Guard C-130s and crews contributed more than 2 million gallons of fire retardant dropped on wild fires throughout the United States.

    Recently, while performing corrosion prevention, the 153rd Maintenance Group discovered the new MAFFS system, which releases retardant through a special nozzle in the paratroop door on the side of the aircraft, had deposited retardant on the elevator tail at the rear of the aircraft, requiring the unit to be replaced.

    With the task laid out for the airmen of the 153 MXG, the behind-the-scenes maintainers started organizing their operations to get the aircraft back to flying status.

    “The only way to get the job done is by working as a team,” said Master Sgt. Roger LaBarr, 30th Airlift Wing ISO dock supervisor.

    This particular project involved multiple shops throughout the array of maintenance operations including: isochronicals, flight line, sheet metal, metals technician, repair and reclamation and even supply.

    “Supply is part of our team,” said LaBarr. “We couldn’t do the job without them.”

    Over the course of a week, quality assurance took pictures of the corrosion, supply ordered necessary parts, and repair and reclamation operated the Omni arm to remove and install the new tail.

    Having so many entities to coordinate takes continuous and detailed planning.

    “Section chiefs from each shop, along with plans and schedules, coordinate how the work is going to get done,” said LaBarr. “They meet two times a day to go over the workload.”

    The installation of the new elevator tail was accomplished thanks to the team members from all aircraft maintenance aspects.

    “This was an intense process,” said LaBarr. “We hadn’t done this type of project in a long time and we couldn’t have done it without teamwork.”