00:15.920 --> 00:17.959
Team , for this month's episode , I

00:17.959 --> 00:20.070
wanna welcome you to Military Sealift

00:20.070 --> 00:22.181
Command's future headquarters here at

00:22.181 --> 00:24.760
Naval Station Norfolk . I'm coming to

00:24.760 --> 00:26.816
you from the top floor of Building X

00:26.816 --> 00:30.600
132 , our 248,000 square

00:30.600 --> 00:32.600
foot future headquarters , and just

00:32.600 --> 00:35.409
look at this view . As it stands ,

00:35.459 --> 00:37.779
we're over 70% finished with this

00:37.779 --> 00:40.139
project , and I know , and I fully

00:40.139 --> 00:42.195
understand this has been a long time

00:42.195 --> 00:44.250
coming , but I hope it will be worth

00:44.250 --> 00:46.361
the wait and the new spaces will meet

00:46.361 --> 00:48.695
the needs of our people and our mission .

00:49.060 --> 00:51.060
Crews are currently wrapping up the

00:51.060 --> 00:53.116
construction phase of X-132 and will

00:53.116 --> 00:55.060
soon shift to the test and balance

00:55.060 --> 00:57.639
phase of this long overdue update .

00:58.229 --> 01:00.340
Before I take you around the building

01:00.340 --> 01:02.562
and show you the current status , let's

01:02.562 --> 01:04.840
take a look back and see where we were .

01:04.959 --> 01:07.070
With some of these photos from just a

01:07.070 --> 01:09.070
few years ago , you can see how far

01:09.070 --> 01:11.015
we've come , and I won't sugarcoat

01:11.015 --> 01:13.181
anything . There's still a way to go ,

01:13.181 --> 01:15.349
but progress is evident on every level

01:15.349 --> 01:17.349
and in every space . I'm incredibly

01:17.349 --> 01:19.571
grateful to everyone involved in taking

01:19.571 --> 01:21.738
this project from concept to reality .

01:21.738 --> 01:23.905
The finish line is in sight , and that

01:23.905 --> 01:25.849
is a big thanks to everyone that's

01:25.849 --> 01:28.071
worked on this . Once we have the green

01:28.071 --> 01:30.127
light to start moving people in , it

01:30.127 --> 01:32.293
will be fantastic to have the majority

01:32.293 --> 01:33.905
of everyone under one roof .

01:33.905 --> 01:35.849
Consolidating MSC will help enable

01:35.849 --> 01:37.793
command unification and provide an

01:37.793 --> 01:39.905
opportunity to improve efficiency and

01:39.905 --> 01:42.127
organizational effectiveness . MSC is a

01:42.127 --> 01:43.793
matrix organization requiring

01:43.793 --> 01:46.139
cross-functional teams for day to day

01:46.139 --> 01:48.919
operations . X132 will help promote

01:48.919 --> 01:51.699
collaboration and synergy across lines

01:51.699 --> 01:53.643
of effort by having subject matter

01:53.643 --> 01:55.810
experts from all programs and codes in

01:55.810 --> 01:57.588
one location . This building is

01:57.588 --> 01:59.870
outfitted for nearly 1600 personnel ,

02:00.150 --> 02:01.928
each with their own workspace ,

02:01.928 --> 02:04.039
including a motorized stand-up desk .

02:04.849 --> 02:08.080
X-132 was designed by and for MSC team

02:08.080 --> 02:10.247
members using an open space concept to

02:10.247 --> 02:12.413
encourage collaboration and teamwork .

02:12.600 --> 02:14.656
Our new headquarters will have Wi Fi

02:14.656 --> 02:16.878
throughout the building , 53 conference

02:16.878 --> 02:19.044
rooms , 10 break rooms , 4 elevators ,

02:19.210 --> 02:21.266
and we're also developing a space to

02:21.266 --> 02:23.990
have our own Micromart inside . Now I

02:23.990 --> 02:25.601
know there are some concerns

02:25.601 --> 02:27.657
specifically surrounding parking and

02:27.657 --> 02:29.669
space . At present , we have a

02:29.669 --> 02:33.070
dedicated parking lot with 866 assigned

02:33.070 --> 02:35.110
spaces . I know the math doesn't

02:35.110 --> 02:36.999
exactly add up with the number of

02:36.999 --> 02:39.166
teammates we have , but we are working

02:39.166 --> 02:41.221
with Naval Station Norfolk and Naval

02:41.221 --> 02:43.054
Facilities Command leadership to

02:43.054 --> 02:45.699
explore alternative solutions . In

02:45.699 --> 02:47.477
terms of space , we'll have the

02:47.477 --> 02:49.643
majority of our staff under one roof ,

02:49.643 --> 02:51.810
which is a major improvement for being

02:51.810 --> 02:53.699
dispersed throughout more than 16

02:53.699 --> 02:55.755
different locations around the naval

02:55.755 --> 02:57.977
station . We will also be holding on to

02:57.977 --> 03:00.199
about 5 other buildings so that we have

03:00.199 --> 03:02.477
adequate space to support our mariners ,

03:02.477 --> 03:04.199
sailors , and civilians . As I

03:04.199 --> 03:06.960
mentioned , we're sitting around 70%

03:06.960 --> 03:09.182
complete with an anticipated completion

03:09.182 --> 03:11.349
date for many parts of the building by

03:11.349 --> 03:13.516
the end of this year . After that , we

03:13.516 --> 03:15.627
still have some work to do to get all

03:15.627 --> 03:17.849
of our staff moved from around the base

03:17.849 --> 03:19.800
and into X 132 . To do that

03:19.800 --> 03:21.856
successfully and safely , we will be

03:21.856 --> 03:24.022
phasing teams in by Encode , hopefully

03:24.022 --> 03:27.410
in the first half of 2027 . As with any

03:27.410 --> 03:30.039
move , X-132 does not come without its

03:30.039 --> 03:32.160
challenges . Available parking and

03:32.160 --> 03:34.104
adequate privacy are among the top

03:34.104 --> 03:36.279
concerns of MSC's workforce , and I am

03:36.279 --> 03:38.168
committed to working on a pathway

03:38.168 --> 03:40.223
forward to address such challenges .

03:40.559 --> 03:42.448
I'm also working with the team to

03:42.448 --> 03:44.559
determine which parts of the building

03:44.559 --> 03:46.781
can and cannot have cell phones brought

03:46.781 --> 03:48.948
into them . Before I sign off , let me

03:48.948 --> 03:51.003
give you a look into the future . As

03:51.003 --> 03:53.226
you can see behind me , these are empty

03:53.226 --> 03:55.448
cubicles with no systems and no light .

03:55.470 --> 03:57.526
But this is what the space will look

03:57.526 --> 03:59.414
like when outfitted with computer

03:59.414 --> 04:01.637
systems , decor , and people . It truly

04:01.637 --> 04:03.748
will be a first-rate facility for our

04:03.748 --> 04:05.859
team . As things continue to progress

04:05.859 --> 04:07.970
and more updates become available , I

04:07.970 --> 04:10.081
will keep you informed . I can't wait

04:10.081 --> 04:12.192
for you to see this space . Just look

04:12.192 --> 04:14.470
at that view . Now that's navy country .

04:14.699 --> 04:17.470
Until next time , stay safe and heave

04:17.470 --> 04:21.179
ho . MSC mariners , sailors and

04:21.179 --> 04:22.779
civilians , we deliver .