WEBVTT

00:01.549 --> 00:04.132
(upbeat music)

00:07.320 --> 00:09.730
- The US Army Corps of
Engineers Nashville District

00:09.730 --> 00:12.690
has reached another huge
milestone with the placement

00:12.690 --> 00:15.380
of the tenth and final concrete shell

00:15.380 --> 00:18.160
for the Kentucky Lock Addition Project.

00:18.160 --> 00:20.580
This is the last piece of what will be

00:20.580 --> 00:24.300
the permanent lock wall for
the new navigation lock.

00:24.300 --> 00:27.510
It will also be used as
part of the cofferdam

00:27.510 --> 00:30.060
in order to do future excavation

00:30.060 --> 00:32.970
and construction in the dry.

00:32.970 --> 00:36.410
- Johnson Brothers, contractor
for the cofferdam project,

00:36.410 --> 00:40.270
set the final shell in
position February 2, 2020

00:40.270 --> 00:42.590
on the river bed below Kentucky Lock,

00:42.590 --> 00:44.790
where it will be part of the cofferdam

00:44.790 --> 00:48.420
and eventually a permanent
part of the new lock wall.

00:48.420 --> 00:51.620
The placement of the
1.7 million pound shell

00:51.620 --> 00:53.440
took place after the Tennessee River

00:53.440 --> 00:55.580
receded to a suitable elevation,

00:55.580 --> 00:59.150
following weeks of
delays due to high water

00:59.150 --> 01:02.720
at Tennessee Valley
Authority's Kentucky Dam.

01:02.720 --> 01:04.800
- We're putting concrete
on top of these shells.

01:04.800 --> 01:07.280
We're adding an additional
24 feet of concrete.

01:07.280 --> 01:09.400
So for the first five shells we placed,

01:09.400 --> 01:10.740
they were high enough out of the water,

01:10.740 --> 01:12.850
we were able to continue to place concrete

01:12.850 --> 01:14.070
on those during high water.

01:14.070 --> 01:16.550
So we haven't been sitting here idle,

01:16.550 --> 01:18.110
the problem is we haven't been working

01:18.110 --> 01:20.040
on the critical work during high water,

01:20.040 --> 01:22.040
and that's setting this tenth shell.

01:22.040 --> 01:23.490
- [Lee] The contractor emphasized

01:23.490 --> 01:26.750
constant communication
and attention to safety.

01:26.750 --> 01:27.800
Throughout the lift,

01:27.800 --> 01:30.400
the main objective involved
keeping the shell level

01:30.400 --> 01:31.934
and inching it into position

01:31.934 --> 01:34.949
because it's difficult to slow
down a heavy weight object,

01:34.949 --> 01:37.290
once it gets moving on the water.

01:37.290 --> 01:40.021
- We'll get it close as possible to grade,

01:40.021 --> 01:42.980
and then we'll tug it on into the keyway.

01:42.980 --> 01:44.830
Once we get it into the keyway,

01:44.830 --> 01:46.265
the divers will assist us

01:46.265 --> 01:48.530
hooking up the post tension rods

01:48.530 --> 01:52.020
that's tied back to the previous monolift,

01:52.020 --> 01:53.930
that's already anchored in concrete.

01:53.930 --> 01:55.830
That keeps the shell from shifting

01:55.830 --> 01:58.980
or moving once we're set and locked in.

01:58.980 --> 02:00.900
- [Lee] The Corps of
Engineers placed the first

02:00.900 --> 02:04.900
of ten concrete shells August 6, 2018.

02:04.900 --> 02:06.290
With each shell placed,

02:06.290 --> 02:07.950
the contractor and Army Engineers

02:07.950 --> 02:10.000
made communication a priority,

02:10.000 --> 02:13.830
to reduce risk and improve
methods and processes.

02:13.830 --> 02:15.580
- This is a massive undertaking,

02:15.580 --> 02:18.990
and it has been since
the fall of 2018 to now

02:18.990 --> 02:22.560
and February of 2020, to set ten of these.

02:22.560 --> 02:24.470
And that just shows that the contractor

02:24.470 --> 02:26.270
and the government both worked together

02:26.270 --> 02:27.470
and was able to do this.

02:28.410 --> 02:30.380
- [Lee] Aspects of the lift and technique

02:30.380 --> 02:33.306
used to place all ten concrete
shells with a gantry crane,

02:33.306 --> 02:36.430
is a unique engineering achievement.

02:36.430 --> 02:38.006
The contractor specifically designed

02:38.006 --> 02:41.690
and constructed the for the
downstream cofferdam contract,

02:41.690 --> 02:44.020
and it proved its worth yet again,

02:44.020 --> 02:46.580
with a final and heaviest lift.

02:46.580 --> 02:49.050
- Once the shell is set in the water

02:49.050 --> 02:50.230
and sitting on the spuds

02:50.230 --> 02:53.233
and we've locked it in with
our PT brackets on the side,

02:54.080 --> 02:56.389
the contractor has a lot of work to do

02:56.389 --> 03:00.839
to pour concrete inside that
shell and lock it in place.

03:00.839 --> 03:02.179
We'll come back in,

03:02.179 --> 03:03.710
maybe in a week or so,

03:03.710 --> 03:04.690
when that work is done

03:04.690 --> 03:06.070
and when all of those
sandbags are in place,

03:06.070 --> 03:06.903
and we'll pour it,

03:06.903 --> 03:08.939
we'll tremie concrete underwater and fill,

03:08.939 --> 03:10.699
what we call the plug,

03:10.699 --> 03:12.199
we'll put the plug in,

03:12.199 --> 03:15.080
which sort of locks the shell in place.

03:15.080 --> 03:15.932
- [Lee] The temporary portion
of the downstream cofferdam

03:15.932 --> 03:20.932
is the final step, that will
make it possible to excavate

03:21.190 --> 03:25.360
and then construct the new
lock in dry conditions.

03:25.360 --> 03:27.534
This is Lee Roberts reporting
for the Nashville District

03:27.534 --> 03:29.774
at the Kentucky Lock Addition Project

03:29.774 --> 03:31.803
in Grand Rivers, Kentucky.

03:33.154 --> 03:35.821
(upbeat music)

