Topping Out Ceremony Marks Investment in Future of Submarine Readiness

Naval Facilities Engineering Systems Command Southeast
Story by Jeffrey Hamlin

Date: 01.30.2026
Posted: 01.30.2026 13:17
News ID: 557198
Topping Out Ceremony Marks Investment in Future of Submarine Readiness

A topping out ceremony was held Jan. 29 to mark a major milestone in the construction of a new facility for the Nuclear Regional Maintenance Department (NRMD) at Naval Submarine Base (NSB) Kings Bay, Georgia.

Hosted by Naval Facilities Engineering Systems Command (NAVFAC) Southeast, the event celebrated the placement of the final steel beam on the structure, symbolizing significant progress toward completion of a centralized, state-of-the-art facility designed to support critical maintenance and repair operations for Trident-equipped submarines.

A topping out ceremony is a tradition that dates back centuries to celebrate when a structure reaches its final height. While some ceremonies involve hoisting a tree or flag, the focus here was on the final beam itself, which was signed by the project's stakeholders, engineers, and construction crews. Its placement serves as a powerful tribute to their hard work and signifies the successful completion of the structural phase.

“This topping out, just over a year after breaking ground, is a testament to the skill and dedication of our team," said NAVFAC Southeast Executive Officer Capt. Elizabeth Durika. "This facility is a critical investment in our nation's strategic deterrence, and this progress brings us one step closer to providing a state-of-the-art space to ensure our submarine force remains ready for decades to come.”

The construction has progressed rapidly since the project began. Lt. Cmdr. John Nurthen, construction management team leader, highlighted the significant accomplishments of the construction team.

"The sheer scale of work accomplished on this site is remarkable. Our partners have moved mountains, literally," said Nurthen. "We removed and excavated over four feet of rock and soil from the entire project site, replacing nearly 35,000 cubic yards of unsuitable soils to create a stable foundation. We have erected over 530 tons of structural steel, drilled and placed nearly 3,000 concrete piles, and poured over 100,000 square feet of structural concrete. This milestone is a credit to the incredible effort of every worker on this project."

The new $136 million facility was announced at a groundbreaking ceremony on Jan. 15, 2025. Its purpose is to consolidate NRMD operations, which are currently scattered across NSB Kings Bay in temporary locations and shared facilities. The centralized hub will include nuclear repair shops, ship services support areas, and applied instruction spaces, significantly enhancing communication and collaboration for the maintenance and repair of Trident-equipped submarines.

The project is being managed by NAVFAC Southeast with BL Harbert International as the primary contractor. It is scheduled for completion by December 2028.

About Naval Submarine Base Kings Bay

As the East Coast home for the Navy's Ohio-class submarine force, Naval Submarine Base Kings Bay operates and maintains the facilities essential for supporting the fleet. The base hosts several major commands, including the Trident Training Facility and Trident Refit Facility—all dedicated to ensuring the operational readiness of the submarines and their crews.

About Naval Facilities Engineering Systems Command Southeast

Naval Facilities Engineering Systems Command Southeast, headquartered in Jacksonville, Florida, provides planning, design, construction, contracting, environmental services, public works, real estate and facility maintenance for the U.S. Navy, Marine Corps, Army, Air Force, Space Force, and other federal agencies across the Southeast. Its area of responsibility covers installations from Charleston, South Carolina, to Corpus Christi, Texas, and extends south to Guantanamo Bay, Cuba.