These portfolios have been created to showcase images captured by military photojournalists. Feel free to download the results of these dedicated service members’ hard work, professional talent and individual approach. We encourage you to visit this site often because we update it frequently.
Electrical workers install wiring into the facade of the main entryway of the Basra chidlren's hospital in Basra, Iraq June 14. The facility is scheduled to open to patients in February 2009 as a pediatric cancer treatment facility.
Taken: 06.14.08 Posted: 06.14.08 BASRA, IQ
A completed form awaits concrete to be poured at the Basra children's hospital in Basra, Iraq June 14. Nine Iraqi construction companies are working together on the facility with coordination from Gulf Region South Corps of Engineers. The hospital is being built to world health standards and will serve as a pediatric cancer treatment facility with over 90 patient beds.
Taken: 06.14.08 Posted: 06.14.08 BASRA, IQ
Water and sewage lines at the construction site of the Basra children's hospital are inspected regularly as the project continues. Gulf Region South Corps of Engineers conducted a site survey June 14 to ensure the nine Iraqi firms working on the project have the materials they need and construction standards are maintained.
Taken: 06.14.08 Posted: 06.14.08 BASRA, IQ
An Iraqi foreman goes over issues with the constuction on the site of the Basra chidlren's hospital in Basra, Iraq June 14. This particular building on the site is going up as living quarters for hospital staff to be housed on site with the hospital. The hospital itself will have more than 90 beds and serve primarily as a pediatric cancer treatment facility.
Taken: 06.14.08 Posted: 06.14.08 BASRA, IQ
An Iraqi foreman goes over issues with the constuction on the site of the Basra chidlren's hospital in Basra, Iraq June 14. This particular building on the site is going up as living quarters for hospital staff to be housed on site with the hospital. The hospital itself will have more than 90 beds and serve primarily as a pediatric cancer treatment facility.
Taken: 06.14.08 Posted: 06.14.08 BASRA, IQ
Part of the main entryway into the Basra children's hospital. The hospital is under construction with 9 Iraqi firms doing the work and being coordinated by the Gulf Region South Coast Corps of Engineers. GRSC visited the site May 2 to check on the progess the Iraqi construction firms are making. The hospital is to begin staffing in January 2009 and open to patients as a cancer treatment facility in February 2009.
Taken: 05.06.08 Posted: 05.12.08 BASRA, IQ
Lt. Cdr. Neil Underwood of meets with one of the project managers from the Basra children's hospital during a visit to the construction site May 2. Underwood is with the Gulf Region South Coast Corps of Engineers and coordinates the efforts of 9 Iraqi firms in building the facility. The BCH is projected to open for patients in February 2009 as a cancer treatment facility for children.
Taken: 05.06.08 Posted: 05.12.08 BASRA, IQ
Randall Lewis (right) an architect with the Gulf Region South Coast Corps of Eningeers looks over work being done at the Basra Children's Hospital in Basra, Iraq May 2. The GRSC engineers work with 9 Iraqi firms on various parts of the hospital with a projected opening of February 2009. The project is one of over 40 the GRSC works with in the Basra area.
Taken: 05.06.08 Posted: 05.12.08 BASRA, IQ
An Iraq construction worker mixes mortar to be used in a facade in the mainn entryway of the Basra Children's Hospital in Basra, Iraq May 2. The Gulf Region South Coast Corps of Engineers is coordinating efforts with 9 different Iraqi firms to build the hospital with a projected opening of February 2009.
Taken: 05.06.08 Posted: 05.12.08 BASRA, IQ
Lt. Cdr. Neil Underwood (in uniform) tours the interior of the Basra children's hospital as workers install electrical wiring to lighting fixtures May 2. The hospital is the first built to this level since the 1970s according to Underwood and will be run to western standards as a cancer treatment facility.
Taken: 05.06.08 Posted: 05.12.08 BASRA, IQ